PENERAPAN METODE PERT PADA PENJADWALAN PEMBANGUNAN TUGU ALUN-ALUN KOTA MOJOKERTO
Abstract
East Java Province consists of approximately 38 cities and regencies, each with iconic buildings that rep square as a symbol of the city. However, the construction process encountered delays, leading to increased resent their regional identity. One example is Mojokerto City, which constructed a monument in the town time and costs for project execution. These issues can be minimized through better work planning, one of which involves the application of the PERT (Program Evaluation and Review Technique) method. PERT uses a probabilistic approach with three time estimates to anticipate delays and align the project schedule. The scheduling evaluation using the PERT method indicates that the work could be completed in 112 days, compared to the existing duration of 180 days. The estimated 112-day duration has a completion probability of 65%.